RM新时代首页

歡迎來(lái)到濱州恒通電力器材有限公司網(wǎng)站,我們竭誠(chéng)為您服務(wù)

行業(yè)新聞
當(dāng)前位置:首頁(yè)-資訊中心>行業(yè)新聞標(biāo)志樁在操作方面需要注意的事項(xiàng)

標(biāo)志樁在操作方面需要注意的事項(xiàng)

來(lái)源:http://customfitstairs.com/ 發(fā)布時(shí)間:日期:2022-06-22 0
標(biāo)志樁在操作方面需要注意:
Attention shall be paid to the operation of sign piles:
1、測(cè)量放線的基準(zhǔn)點(diǎn)一定要采用GPS定位,其中放線基準(zhǔn)點(diǎn)是指設(shè)計(jì)控制樁和水準(zhǔn)基樁。
1. GPS positioning must be adopted for the datum point of Surveying and setting out. The datum point of setting out refers to the design control pile and leveling pile.
2、一定要按照?qǐng)D紙的作業(yè)要求設(shè)置控制樁,一定要表明樁號(hào)、里程、地面標(biāo)高、轉(zhuǎn)角高度等數(shù)據(jù)。
2. The control piles must be set according to the operation requirements of the drawings, and the data such as pile number, mileage, ground elevation and corner height must be indicated.
3、在定測(cè)資料和平面或是斷面圖紙上表明地下的障礙物,其次是,要保證線路和地下構(gòu)筑物交叉兩側(cè)的控制范圍為3米,同時(shí),需要設(shè)置警告牌和標(biāo)志樁。標(biāo)志樁上需要寫(xiě)上相關(guān)的數(shù)據(jù)。比如:埋深,交叉尺寸等。
3. Indicate the underground obstacles on the location survey data and plane or section drawings. Secondly, ensure that the control range on both sides of the intersection of the line and underground structures is 3M. At the same time, set warning signs and sign piles. Relevant data shall be written on the sign pile. For example, burial depth, crossing size, etc.
4、關(guān)于劃線方面,要根據(jù)軸線和標(biāo)志樁的界限之間拉一根繩子,撒上白石灰劃線。完成劃線,要清理現(xiàn)場(chǎng)的障礙物。
4. As for the marking, a rope shall be pulled between the axis and the boundary of the sign pile, and white lime shall be sprinkled for marking. After finishing the marking, the obstacles on the site shall be cleared.
5、關(guān)于移樁方面,是在劃線完成之后打掃清理之前,將所有需要的線管樁平移到土堆的旁邊,范圍控制在0.3m。
5. In terms of pile moving, all required pipeline piles shall be moved to the side of the soil pile after the completion of marking and before cleaning, and the range shall be controlled within 0.3m.

相關(guān)產(chǎn)品 / Related products

  • 地釘

    地釘

  • 地釘

    地釘

  • 警示樁

    警示樁

  • 警示樁

    警示樁

截屏,微信識(shí)別二維碼

RM新时代首页